This Annex provides a consolidation of the mitigation measures recommended for the Project. The consolidation is presented in the form of an Implementation Schedule in accordance with the format specified in Section 3.4.7.3 of the EIA Study Brief No. ESB-112/2004.
The Implementation Schedule has the following column headings:
EIA Ref
This denotes the section number or reference from the EIA Report Main text.
EM&A Log Ref
This denotes the sequential number of each of the recommended mitigation measures specified in the Implementation Schedule.
Environmental Protection Measures
This denotes the recommended mitigation measures, courses of action or subsequent deliverables that are to be adopted, undertaken or delivered to avoid, minimise or ameliorate predicted environmental impacts.
Objectives
This denotes the objectives of the recommended mitigation measures and main concerns to address.
Location/Duration of Measures/Timing of Completion of Measures
This indicates the spatial area in which the recommended mitigation measures are to be implemented together with details of the programming or timing of their implementation.
This denotes where the responsibility lies for the implementation of the recommended mitigation measures.
This denotes the stage at which the recommended mitigation measures are to be implemented either during the Design, Construction, Operation or Decommissioning.
Relevant Legislation
This section defines the controlling legislation that is required to be complied with.
Implementation
Schedule
EIA* Ref. |
EM&A Log Ref |
Environmental Protection
Measures |
Objectives |
Location/Duration of
Measures/Timing of Completion of Measures |
Implementation Agent |
Implementation Stage** |
Relevant Legislation &
Guidelines |
||||||||||||||
|
|
|
|
|
|
Des |
C |
O |
Dec |
|
|||||||||||
|
|
Noise -
Construction Phase |
|
|
|
|
|
|
|
|
|||||||||||
4.7.1 |
1 |
Good Site
Practices · Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works; · Machines and plant that may be use intermittently, such as vibratory poker, should be shut down between work periods or should be throttled down to a minimum; · Plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from nearby NSRs; and · Mobile plant should be sited as far away from NSRs as possible. |
To minimise potential noise nuisance arising from the works to nearby NSRs. |
During Construction stage |
Construction Contractor |
|
ü |
|
|
Noise Control Ordinance (NCO) and Annex 5 of the EIAO TM |
|||||||||||
|
|
Noise -
Operation Phase |
|
|
|
|
|
|
|
|
|||||||||||
4.7.2 |
2 |
The allowable
maximum sound power level of 100 dB(A) and pure tone free shall be included in
the tender specification of wind turbine. |
To minimise potential noise nuisance arising from operation of wind turbine |
During detailed design stage |
HEC |
ü |
|
ü |
|
Noise Control Ordinance (NCO) and Annex 5 of the EIAO TM |
|||||||||||
|
|
Ecology – Construction
Phase |
|
|
|
|
|
|
|
|
|||||||||||
5.11.2 |
3 |
Measures for
Romer’s Tree Frog · Undertake one day-time and one night-time survey for the Romer’s Tree Frog within the Project Area just before the construction works commence. The surveyor(s) should actively search within the Project Area paying special attention to the water bodies (ie abandoned containers). All recorded Romer’s Tree Frog (adults and tadpoles) must be caught by hand and translocated to the stream pools of middle course of Stream S4 near Lo Tik Wan, the critical natural habitat for the Romer’s Tree Frog within the Study Area, immediately after the survey. The Romer’s Tree Frog surveys and translocation works shall be undertaken by a qualified ecologist with at least five years of relevant experience in faunal translocation works. |
To avoid impacts on the Romer’s Tree Frog arising from the work |
Prior to commence of construction |
HEC/ Construction Contractor |
|
ü |
|
|
|
|||||||||||
5.11.2 |
4 |
Measures for Construction
Runoff · Surface run-off from the construction site should be directed into existing stream channel via adequately designed sand/silt removal facilities such as sand traps, silt traps and sediment basins. Channels, earth bunds or sand bag barriers should be provided on site to properly direct stormwater to such silt removal facilities. |
To minimise potential ecological impacts arising from the works |
During construction |
Construction Contractor |
|
ü |
|
|
|
|||||||||||
5.11.2 |
5 |
Good Construction
Practice ·
Erect fences along the boundary of the works area before the
commencement of works to prevent tipping, vehicle movements, and encroachment
of personnel onto adjacent areas.
·
Avoid any damage and disturbance, particularly those caused by
filling and illegal dumping, to the remaining and surrounding natural stream
habitats. ·
Regularly check the work site boundaries to ensure that they are not
breached and that no damage occurs to surrounding areas. ·
Prohibit and prevent open fires within the site boundary during
construction and provide temporary fire fighting equipment in the Project
Area. |
To minimise potential ecological impacts arising from the works |
During construction |
Construction Contractor |
|
ü |
|
|
|
|||||||||||
|
|
· Treat any damage that may have occurred to individual major trees in the adjacent area and along the 275 kV Cable Route (used to transport the construction materials) with surgery. · Reinstate temporary disturbed areas immediately after completion of the construction works, ie through on-site tree/shrub planting. Tree/shrub species used should make reference from those in the surrounding area and/or Annex C of EIA report. |
|
|
|
|
|
|
|
|
|||||||||||
|
|
Ecology – Operation
Phase |
|
|
|
|
|
|
|
|
|||||||||||
5.11.3 |
6 |
No mitigation measures are required. See EM&A Manual for monitoring requirements. |
|
|
|
|
|
|
|
|
|||||||||||
|
Landscape and Visual – Construction Phase |
|
|
|
|
|
|
|
|
||||||||||||
6.7 |
7 |
·
Colour scheme and non-reflective paints will be
made to enable the proposed wind turbine to blend in well with natural
surroundings and minimise the visual intrusion. ·
Selection
of low rotating speed machine to minimize the visual disturbance. |
To minimum potential landscape and
visual impacts arising from the works |
Prior commence of construction |
Construction Contractor |
ü |
ü |
|
|
|
|||||||||||
6.7 |
|
·
New
cut and fill slopes and other land affected by construction works would
be reinstated to natural land form and topography of
the natural slope as far as practical. Grading of these slopes to resemble a
natural, rolling landform similar to that of adjacent topography would be
carried out. Approximately 1,400 sq.m. of disturbed areas would be
reinstated. ·
Appropriate
landscape planting including trees, shrubs and grasses (approx. 1,400 sq.m.) will be provided to soften the ground level appearance of the proposed
wind turbine site. ·
Existing soil resources on site from the cut
slope will be re-used for backfilling at site as far as practicable to
minimize the need to import or export soils. |
To minimum potential landscape and
visual impacts arising from the works |
During construction |
HEC/ Construction Contractor |
ü ü ü |
ü ü ü |
ü |
|
|
|||||||||||
|
|
Landscape and Visual - Operation Phase |
|
|
|
|
|
|
|
|
|||||||||||
|
8 |
No mitigation measures are
required. See EM&A Manual
for monitoring requirements. |
|
|
|
|
|
|
|
|
|||||||||||
|
|
Air Quality - Construction Phase |
|
|
|
|
|
|
|
|
|||||||||||
7.5.1 |
9 |
·
Covering
entirely by impervious sheet or frequently watering of the on-site stockpile
of excavated materials to keep wet always before backfilling; ·
Frequent
watering of exposed area or worksite of excavation to maintain surface wet, if necessary and practical; ·
Provision of
vehicle washing to remove any dusting materials from small village trucks’
body and wheel at the exit of worksite; ·
Well-maintained
diesel-powered mechanical equipment to avoid black smoke emissions; and ·
Shut-down of
diesel-powered mechanical equipment or trucks inside the worksites when they
are not in operation. |
To minimise potential dust nuisance arising from the works |
During construction |
Construction Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
|||||||||||
|
|
Air Quality - Operation Phase |
|
|
|
|
|
|
|
|
|||||||||||
7.5.2 |
10 |
N/A |
|
|
|
|
|
|
|
|
|||||||||||
|
WATER QUALITY - Construction Phase |
|
|
|
|
|
|
|
|
||||||||||||
8.6.1 |
11 |
Surface
Run-off ·
Surface run-off from the
construction site should be directed into existing stream channel via
adequately designed sand/silt removal facilities such as sand traps, silt
traps and sediment basins.
Channels, earth bunds or sand bag barriers should be provided on site
to properly direct stormwater to such silt removal facilities. |
To minimise potential water quality impacts arising from the works |
During construction |
Construction Contractor |
|
ü |
|
|
|
|||||||||||
|
|
· Silt removal facilities should be maintained and the deposited silt and grit should be removed regularly, at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times. · During excavation in the wet season, temporarily exposed soil surfaces should be covered, eg by tarpaulin, and temporary access roads should be protected by crushed stone or gravel, as excavation proceeds. Intercepting channels should be provided (eg along the crest/edge of the excavation) to prevent storm runoff from washing across exposed soil surfaces. Arrangements should always be in place to ensure that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm. · Earthworks final surfaces should be well compacted and the subsequent permanent work or surface protection should be carried out as soon as practical after the final surface are formed to prevent erosion caused by rainstorms. Appropriate intercepting channels should be provided where necessary. Rainwater pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities. · Open stockpiles of construction materials (eg aggregates and sand) on site should be covered with tarpaulin similar fabric during rainstorms. Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system. |
|
|
|
|
|
|
|
|
|||||||||||
8.6.2 |
12 |
Wastewater from Site Facilities · The use of chemical toilets will be necessary and these should be provided by a licensed contractor, who will be responsible for appropriate disposal and maintenance of these facilities. |
To minimise potential water quality impacts arising from the works |
During construction |
Construction Contractor |
|
ü |
|
|
|
|||||||||||
|
|
WATER QUALITY - Operation Phase |
|
|
|
|
|
|
|
|
|||||||||||
8.7.2 |
13 |
No mitigation measures are required. |
|
|
|
|
|
|
|
|
|||||||||||
|
|
WASTE- Construction Phase |
|
|
|
|
|
|
|
|
|||||||||||
3.5 |
14 |
· Excavated materials should be used as backfill as far as practicable; |
To enhance reuse, recycling and, as appropriate, proper disposal of excavated materials
|
Project site/during construction |
Construction Contractors |
|
ü |
|
|
ETWBTC No 34/2002; ETWBTC No 15/2003 |
|||||||||||
|
|
· Excavated materials should be segregated from other wastes; and |
To avoid contamination thereby ensuring acceptability at public filling areas and avoiding the need for landfill disposal |
|
|
|
|
|
|
|
|||||||||||
|
|
· Works activities should be limited within the site boundary; and · Filling and illegal dumping should be inhibited through site management and audit. |
To ensure that adverse environmental impacts are prevented |
|
|
|
|
|
|
|
|||||||||||
|
|
Waste - Operation Phase |
|
|
|
|
|
|
|
|
|||||||||||
3.5 |
15 |
No mitigation measures are required. |
|
|
|
|
|
|
|
|
|||||||||||